Superior Tribunal de Justiça, 30 July 2025, Case No. HDE No. 7190 - EX
(Swire Shipping Pte. Ltd., also known as The China Navigation Company Pte Ltd v. Buritirama Mineracao S.A. – Bankrupt Estate)
BRAZIL 79
The Superior Court of Justice granted recognition of an award rendered in England. When the respondent failed to pay under the settlement agreement that had concluded an initial arbitration between the parties in respect of a demurrage claim, the applicant appointed an arbitrator to resume the proceedings. The respondent did not avail itself of its right to appoint a different arbitrator, and, according to the terms of the charterparty, the appointed arbitrator proceeded as sole arbitrator. The Court dismissed the argument of the respondent that it had not been notified of the second arbitration, reasoning that, since the settlement amount had not been paid, it was proper to resume the proceeding. The Court also held that the fact that recognition could be granted even if the respondent had been declared in bankruptcy after the award’s rendition. The Brazilian law provisions on bankruptcy would only become relevant at the enforcement stage.
The court discusses the principle that the procedure for the enforcement of awards under the Convention is governed by the lex fori, as well as procedural issues (such as the competent enforcement court) not falling under the specific cases of ¶¶ 302-307.
The court discusses how to determine whether the document supplied is an award capable of being recognized and enforced, including whether the award is duly authenticated, and whether a copy is duly certified; whether a prior interim and/or partial award should be supplied together with the final award.
The court discusses issues relating to the manner of authentication and certification of the award and/or arbitration agreement.
The court discusses issues relating to the requirements of the translation (translation by sworn translator, translation of entire award etc.) and whether a translation is necessary.
The court discusses the overall scheme and/or pro-enforcement bias of the Convention.
The court discusses questions relating to the general approach taken by the Convention to the grounds for refusal of recognition and enforcement, including its pro-enforcement bias, as well as the system of the Convention, under which recognition and enforcement may only be denied on seven listed grounds and the petitioner has only the obligations set out in Art. IV.
The court discusses the principle that the merits of the award may not be reviewed and that the court may only carry out a limited review of the award to ascertain grounds for refusal.
Due process: The court discusses what constitutes “proper notice” of the appointment of the arbitrators or of the arbitration proceedings.